Technical Meeting in Milano, April 10-11, 2019
A technical meeting took place in Milano, on April 10-11, 2019 hosted by partner "Lutech SpA".
The main decision points were:
1. Prototype 1: Updated Specifications (Reported by each technical partner via a Progress Report Template Circulated by SLG.
2. A compromising approach regarding the dark web task will be described by LTEC and reviewed/agreed by UAB and the overall consortium.
3. Next Technical Meeting to be held on June 11th and 12th at Ilmenau FHG.
4. Prototype specifications can only be adjusted following gitlab ‘issues’ processes
5. The remaining sprints towards Prototype 1 preparedness are: SPRINT 2 (June 2019), SPRINT 3 (July 2019), SPRINT 3 (August 2019)